Dispatch Center Project Photos

Please be patient. Depending on your connection speed, it may take a few minutes for all of the photos to load. Also, please understand that interior photos will be limited for security reasons.

January 7, 2009

Joint Communications' future site as seen from Oross Street and East Liberty Street
Septagon Construction sign at Joint Communications' future site

March 12, 2009 - Excavation began

Bulldozer leveling the area for the new facility
Bulldozer leveling the area for the new facility

March 15, 2009 - Groundbreaking Ceremony

Groundbreaking Ceremony
Pictured from left to right: Superintendent Tom Norling (Septagon Construction Co, Inc), Vice Chairman Ken Hoover (Emergency Services Board), Chairman Cliff Gronauer (Emergency Services Board), Construction Consultant Brian Maenner (Septagon Construction Co, Inc), Board Member Harry Divins (Emergency Services Board), Board Member Ed Lang (Emergency Services Board), 911 Director Chris Hardin (Joint Communications), Board Member Paul Day (Emergency Services Board), Board Member Jack Allison (Emergency Services Board), Assistant 911 Director Dan Barnett (Joint Communications), and Dispatch Supervisor Shelly Rahmouni (Joint Communications).
Not pictured: Board Member Bill Arndt (Emergency Services Board).

March 24, 2009 - Exterior rendering released

Exterior rendering of the new facility

March 25, 2009 - The footers have been poured and the forms are going up for more concrete

View of work site
Concrete forms
Concrete forms

March 30, 2009 - Final rendering released

Final exterior rendering of the new facility

April 15, 2009 - Concrete floor poured

Cement truck delivering concrete
Cement pumper distributing the concrete

April 22, 2009 - Bedford Masonry laying block

Bedford Masonry truck on site
Block has been laid

May 2, 2009 - Bedford Masonry continues laying block

Block on north side of building
Block on northwest corner of building

May 18, 2009 - Most of the exterior block has been laid

East wall
Southeast corner

June 9, 2009 - The exterior walls are up and work continues

Front of building
Front of building
North side of building

June 18, 2009 - Generator delivered, sidewalks being poured and interior walls being framed

Front of building showing generator
Back of building showing sidewalk
Interior framing
Interior framing

July 16, 2009 - Brick is finished

Entrance canopy complete
Front of building

July 22, 2009 - Excavation underway for radio tower

Digging hole for radio tower foundation

August 10, 2009 - The parking lot has been paved and lined

Main entrance parking
South parking area

August 13, 2009 - Radio tower construction underway

Radio tower legs assembled

August 18, 2009 - Radio tower construction complete

Tower section being raised into place
All tower sections in place
Radio tower completed

August 21, 2009 - Glass has been installed in the windows and front door. Landscaping being done.

Glass has been installed in the windows
Hampton's Landscaping working on the landscaping.

September 11, 2009 - Dispatch consoles installed.

Dispatch consoles
Dispatch console

September 13, 2009 - Antennas being installed on the radio tower.

Antenna being raised into position
Antenna being installed

September 18, 2009 - Mid Mo Signs has finished installing the lettering on the building.

911 over the entrance
Audrain County Joint Communications on the front of the building

September 25, 2009 - Septagon has installed the lobby plaque.

Plaque in lobby

September 29, 2009 - Vandiver Village has installed the Dispatch Drive sign at Oross Street.

Dispatch Drive sign hung at Oross Street in Vandiver Village
 